The aim of work is to get an insight over the essential theme of “variances during building and civil construction”. In the very first place, I studied the Italian legislation`s regulation about this theme, in a second time, I analysed some real cases I have faced in first person during my thesis-internship at “Inter-studio Engineering Solutions”, in an construction engineering firm) In particular I analysed an aqueduct and sewer system realization. This service is longer than 4 km and it is located in two Milan’s outskirt districts, Trezzo sull’Adda and Cornate d’Adda. This project is named 4541-D1 by Cap Holding Spa. From the same company I took two other cheaper, less significant and similar projects which present little cost-variations during the construction. Afterward I compared these works with the main construction in Trezzo sull'Adda. In this work Risk Management System is a fundamental tool in order to understand which possible strategy can be adopted to reduce the variances during construction. For instance, it is really recommended to adopt Risk Management System in order to evaluate when a preliminary action has to be planned. In this way, I was able to determine whenever a preliminary action is a necessary cost-increase operation that has to be taken, or whenever the low-risk associate with such a kind of intervention allows to take the risk of avoiding such a kind of act. Given that the Risk Management System is used in different sectors, I have studied some management techniques used in business organizations, in building constructions and in civil sector. In this way, I developed a specific model to estimate the associated in this kind of project. In closing, given the lack of other similar projects which suit such a study, I requested to experts in this field to complete a questionnaire. In this way I processed some statistical graphics where there are the total number of construction with cost-variances compared to others without these problems.

Il fine che si vuole raggiungere con l’elaborato seguente è quello di approfondire la propria conoscenza riguardo il tema fondamentale delle varianti in corso d’opera, studiando dapprima ciò che viene riportato nella normativa italiana e, successivamente, analizzando dei casi reali a cui si è partecipato direttamente durante un’esperienza di stage presso uno studio di ingegneria. Nello specifico è stata analizzata la realizzazione di una rete acquedottistica e fognaria lunga più di 4 km e localizzata nei comuni di Trezzo sull’Adda e Cornate d’Adda (prog. 4541-D1 della società Cap Holding Spa) e il confronto con altri due lavori di natura simile ma di minore entità, sempre dello stesso committente. A questo studio si applica un sistema di gestione del rischio (Risk Management), il quale viene impiegato per comprendere le possibili strategie da adottare in questi casi, più precisamente dove era possibile prendersi il rischio di non effettuare determinate indagini preliminari e dove invece tale rischio è stato troppo azzardato. In questo secondo caso la prevenzione sarebbe stata la scelta più indicata rispetto al rischio. Siccome il Risk Management viene utilizzato in vari settori, sono state studiate le varie tecniche di gestione del rischio impiegate nelle organizzazioni aziendali, nell'edilizia e nei lavori infrastrutturali, così da poter sviluppare un proprio modello di gestione del rischio specifico per questo genere di lavoro. Infine, data la carenza di altri lavori simili da poter esaminare, viene data un’impronta statistica tramite l’utilizzo di questionari compilati da degli esperti nella loro esperienza con questo tipo di lavori civili e ambientali.

Varianti in corso d'opera. Analisi e valutazioni tecniche ed organizzativa applicate alla realizzazione di infrastrutture idrauliche

GALIERO, DANIELE
2014/2015

Abstract

The aim of work is to get an insight over the essential theme of “variances during building and civil construction”. In the very first place, I studied the Italian legislation`s regulation about this theme, in a second time, I analysed some real cases I have faced in first person during my thesis-internship at “Inter-studio Engineering Solutions”, in an construction engineering firm) In particular I analysed an aqueduct and sewer system realization. This service is longer than 4 km and it is located in two Milan’s outskirt districts, Trezzo sull’Adda and Cornate d’Adda. This project is named 4541-D1 by Cap Holding Spa. From the same company I took two other cheaper, less significant and similar projects which present little cost-variations during the construction. Afterward I compared these works with the main construction in Trezzo sull'Adda. In this work Risk Management System is a fundamental tool in order to understand which possible strategy can be adopted to reduce the variances during construction. For instance, it is really recommended to adopt Risk Management System in order to evaluate when a preliminary action has to be planned. In this way, I was able to determine whenever a preliminary action is a necessary cost-increase operation that has to be taken, or whenever the low-risk associate with such a kind of intervention allows to take the risk of avoiding such a kind of act. Given that the Risk Management System is used in different sectors, I have studied some management techniques used in business organizations, in building constructions and in civil sector. In this way, I developed a specific model to estimate the associated in this kind of project. In closing, given the lack of other similar projects which suit such a study, I requested to experts in this field to complete a questionnaire. In this way I processed some statistical graphics where there are the total number of construction with cost-variances compared to others without these problems.
ARC I - Scuola di Architettura Urbanistica Ingegneria delle Costruzioni
27-apr-2016
2014/2015
Il fine che si vuole raggiungere con l’elaborato seguente è quello di approfondire la propria conoscenza riguardo il tema fondamentale delle varianti in corso d’opera, studiando dapprima ciò che viene riportato nella normativa italiana e, successivamente, analizzando dei casi reali a cui si è partecipato direttamente durante un’esperienza di stage presso uno studio di ingegneria. Nello specifico è stata analizzata la realizzazione di una rete acquedottistica e fognaria lunga più di 4 km e localizzata nei comuni di Trezzo sull’Adda e Cornate d’Adda (prog. 4541-D1 della società Cap Holding Spa) e il confronto con altri due lavori di natura simile ma di minore entità, sempre dello stesso committente. A questo studio si applica un sistema di gestione del rischio (Risk Management), il quale viene impiegato per comprendere le possibili strategie da adottare in questi casi, più precisamente dove era possibile prendersi il rischio di non effettuare determinate indagini preliminari e dove invece tale rischio è stato troppo azzardato. In questo secondo caso la prevenzione sarebbe stata la scelta più indicata rispetto al rischio. Siccome il Risk Management viene utilizzato in vari settori, sono state studiate le varie tecniche di gestione del rischio impiegate nelle organizzazioni aziendali, nell'edilizia e nei lavori infrastrutturali, così da poter sviluppare un proprio modello di gestione del rischio specifico per questo genere di lavoro. Infine, data la carenza di altri lavori simili da poter esaminare, viene data un’impronta statistica tramite l’utilizzo di questionari compilati da degli esperti nella loro esperienza con questo tipo di lavori civili e ambientali.
Tesi di laurea Magistrale
File allegati
File Dimensione Formato  
2016_04_GALIERO.pdf

non accessibile

Descrizione: 2016_04_GALIERO
Dimensione 12.9 MB
Formato Adobe PDF
12.9 MB Adobe PDF   Visualizza/Apri
2016_04_GALIERO_ALLEGATI.pdf

solo utenti autorizzati dal 09/04/2017

Descrizione: 2016_04_GALIERO_ALLEGATI
Dimensione 1.85 MB
Formato Adobe PDF
1.85 MB Adobe PDF   Visualizza/Apri

I documenti in POLITesi sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/10589/121224