The aim of this work is to ensure the correct transfer of computational information necessary for the correct management of the contract, starting from the Building Information Modeling (BIM) and using this tool to generate a complete data flow able to deal with computational and management software of the ACCA. The exchange of data and the correct computation of a work are the basis for the success of the project; traditional methods involving analytical control with CAD drawing and manual transcription to Excel are cumbersome and may therefore have a negative effect on efficiency, leading inevitably the designer to errors in reading and transcription. In the field of construction, such errors result in an increase in costs, time and failure to achieve the objectives, with a relative reduction in the quality of works and risks for workers’ safety, leading inexorably to the failure of the project. The software that will be used during this thesis is used as a model through which the designer and the enterprise can obtain a flow and an exchange of information to guarantee a correct vision of the whole work. The thesis will be divided into two phases: in the first one, the problems related to the computation performed with the BIM method will be analyzed, studying the advantages and disadvantages that this tool provides, proposing the appropriate solutions. In the second one, as a practical case, the contract management will be performed on the basis of the data elaborated in Phase 1. Specifically, the following critical points will be analyzed: • analysis of missing or otherwise not explicit parameters within the Revit model; • creation of computational rules to minimize errors in the software Revit; • export and reorder of data from Revit to Primus, minimizing the imputations to avoid typing errors; • analysis, management and resolution of critical issues due to changes in work design; • management of the contract of an existing enterprise, through the Impresus software, analyzing criticalities that can arise during the planning process, proposing solutions that can simplify the organization of the enterprise. The aim is to verify whether with BIM methodology and order automation with ACCA software, it is possible for a construction company to pursue the correct achievement of the works, in compliance with timeframe, costs and objectives.
L’obiettivo del lavoro è garantire il corretto trasferimento di informazioni computazionali necessarie per la corretta gestione della commessa, partendo dal Building Information Modeling (BIM) e sfruttando questo strumento per generare un flusso completo in grado di dialogare con i software computazionali e gestionali della ACCA. Lo scambio di dati e la corretta computazione di un’opera sono alla base per il successo della commessa; i metodi tradizionali che prevedono un controllo analitico tramite disegno CAD e trascrizione manuale su Excel sono, infatti, macchinosi e possono quindi incidere negativamente sulla durata del lavoro, portando inevitabilmente il progettista a commettere degli errori di lettura e trascrizione. Nel campo delle costruzioni, tali errori si traducono nell’ aumento di costi, tempi e mancato conseguimento degli obiettivi, con relativo abbassamento della qualità dei lavori e rischi per la sicurezza dei lavoratori, portando inesorabilmente al fallimento della commessa. I software che saranno impiegati durante questa tesi si pongono come un modello attraverso il quale il progettista e l’impresa possono ottenere un flusso ed uno scambio di informazioni tale da garantire una corretta visione d’insieme della commessa. La tesi sarà suddivisa in due fasi: nella prima saranno analizzate le problematiche relative alla computazione eseguita con il metodo BIM, studiando vantaggi e svantaggi che questo strumento ci fornisce, proponendo le dovute soluzioni. Nella seconda, invece, sarà eseguita, come caso pratico, la gestione della commessa sulla base dei dati elaborati nella Fase I. Nello specifico i punti critici che saranno analizzati sono i seguenti: • analisi delle voci e dei parametri mancanti o comunque non esplicitati all’interno del modello Revit; • creazione di regole computazionali in grado di ridurre al minimo gli errori presenti nel software Revit; • esportazione e riordino del computo da Revit a Primus, riducendo al minimo le imputazioni da parte del professionista per evitare errori di digitazione; • analisi, gestione e soluzione delle criticità dovute alle modifiche in fase di progettazione sulla computazione dell’opera; • gestione della commessa di un’impresa realmente esistente, tramite il software Impresus, analizzando le criticità che possono sorgere nell’arco dell’intero iter progettuale, proponendo delle soluzioni che possano semplificare l’organizzazione dell’impresa. L’intento è quello di verificare se con la metodologia BIM e l’automatizzazione della commessa con i software ACCA, è possibile per un’impresa di costruzioni perseguire un più corretto completamento dei lavori nel rispetto di tempi, costi e obiettivi.
Analisi e riorganizzazione dei flussi progettuali per la corretta gestione della commessa
MESSINA, DAVIDE;CELESTE, LUIGI
2018/2019
Abstract
The aim of this work is to ensure the correct transfer of computational information necessary for the correct management of the contract, starting from the Building Information Modeling (BIM) and using this tool to generate a complete data flow able to deal with computational and management software of the ACCA. The exchange of data and the correct computation of a work are the basis for the success of the project; traditional methods involving analytical control with CAD drawing and manual transcription to Excel are cumbersome and may therefore have a negative effect on efficiency, leading inevitably the designer to errors in reading and transcription. In the field of construction, such errors result in an increase in costs, time and failure to achieve the objectives, with a relative reduction in the quality of works and risks for workers’ safety, leading inexorably to the failure of the project. The software that will be used during this thesis is used as a model through which the designer and the enterprise can obtain a flow and an exchange of information to guarantee a correct vision of the whole work. The thesis will be divided into two phases: in the first one, the problems related to the computation performed with the BIM method will be analyzed, studying the advantages and disadvantages that this tool provides, proposing the appropriate solutions. In the second one, as a practical case, the contract management will be performed on the basis of the data elaborated in Phase 1. Specifically, the following critical points will be analyzed: • analysis of missing or otherwise not explicit parameters within the Revit model; • creation of computational rules to minimize errors in the software Revit; • export and reorder of data from Revit to Primus, minimizing the imputations to avoid typing errors; • analysis, management and resolution of critical issues due to changes in work design; • management of the contract of an existing enterprise, through the Impresus software, analyzing criticalities that can arise during the planning process, proposing solutions that can simplify the organization of the enterprise. The aim is to verify whether with BIM methodology and order automation with ACCA software, it is possible for a construction company to pursue the correct achievement of the works, in compliance with timeframe, costs and objectives.File | Dimensione | Formato | |
---|---|---|---|
EF a 19 1127_EXCELa_Sintesi abachi.pdf
non accessibile
Descrizione: Allegato - Tabella abachi 1
Dimensione
995.31 kB
Formato
Adobe PDF
|
995.31 kB | Adobe PDF | Visualizza/Apri |
EF a 19 1127_EXCELb_Sintesi abachi.pdf
non accessibile
Descrizione: Allegato - Tabella abachi 2
Dimensione
77.23 kB
Formato
Adobe PDF
|
77.23 kB | Adobe PDF | Visualizza/Apri |
EF a 19 1127_EXCELc_Sintesi abachi.pdf
non accessibile
Descrizione: Allegato - Tabella abachi 3
Dimensione
233.25 kB
Formato
Adobe PDF
|
233.25 kB | Adobe PDF | Visualizza/Apri |
EF a 19 1127_EXCELd_Sintesi abachi.pdf
non accessibile
Descrizione: Allegato - Tabella abachi 4
Dimensione
79.21 kB
Formato
Adobe PDF
|
79.21 kB | Adobe PDF | Visualizza/Apri |
EF a 19 1127_EXCELe_Sintesi abachi.pdf
non accessibile
Descrizione: Allegato - Tabella abachi 5
Dimensione
343.19 kB
Formato
Adobe PDF
|
343.19 kB | Adobe PDF | Visualizza/Apri |
EF a 19 1127_EXCELf_Sintesi abachi.pdf
non accessibile
Descrizione: Allegato - Tabella abachi 6
Dimensione
97.81 kB
Formato
Adobe PDF
|
97.81 kB | Adobe PDF | Visualizza/Apri |
EF b 19 1127_PRIMUS_Computo Metrico.pdf
non accessibile
Descrizione: Allegato - Computo Metrico
Dimensione
569.39 kB
Formato
Adobe PDF
|
569.39 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSa_Attrezzi.PDF
non accessibile
Descrizione: Allegato - Tabella di Gestione della Commessa 1
Dimensione
28.34 kB
Formato
Adobe PDF
|
28.34 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSb_Noli.PDF
non accessibile
Descrizione: Allegato - Tabella di Gestione della Commessa 2
Dimensione
23.33 kB
Formato
Adobe PDF
|
23.33 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSc_Dipendenti.PDF
non accessibile
Descrizione: Allegato - Tabella di Gestione della Commessa 3
Dimensione
63.81 kB
Formato
Adobe PDF
|
63.81 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSd_Risorse.pdf
non accessibile
Descrizione: Allegato - Tabella di Gestione della Commessa 4
Dimensione
295.01 kB
Formato
Adobe PDF
|
295.01 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSe_Analisi Prezzi.pdf
non accessibile
Descrizione: Allegato - Tabella di Gestione della Commessa 5
Dimensione
125.97 kB
Formato
Adobe PDF
|
125.97 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSf_Gantt.pdf
non accessibile
Descrizione: Allegato - Diagramma di Gantt
Dimensione
234.68 kB
Formato
Adobe PDF
|
234.68 kB | Adobe PDF | Visualizza/Apri |
EF c 19 1127_IMPRESUSg_Rapporto Gantt.pdf
non accessibile
Descrizione: Allegato - Tabella di Gestione della Commessa 6
Dimensione
563.03 kB
Formato
Adobe PDF
|
563.03 kB | Adobe PDF | Visualizza/Apri |
EF d 19 1127_CERTUS_PSC.pdf
non accessibile
Descrizione: Allegato - Estratto dal Piano Sicurezza e Coordinamento
Dimensione
1.92 MB
Formato
Adobe PDF
|
1.92 MB | Adobe PDF | Visualizza/Apri |
EF e 19 1127_Abachi_Computo.xlsx
non accessibile
Descrizione: Allegato - Tabelle su fogli elettronici
Dimensione
625.16 kB
Formato
Microsoft Excel XML
|
625.16 kB | Microsoft Excel XML | Visualizza/Apri |
EF f 19 1127_Computo Metrico.dcf
non accessibile
Descrizione: Allegato - Computo Metrico
Dimensione
164.27 kB
Formato
Document Computation Format
|
164.27 kB | Document Computation Format | Visualizza/Apri |
EF g 19 1127_Gestione della Commessa.ZIP
non accessibile
Descrizione: Allegato - Backup del software di Gestione della Commessa
Dimensione
5.32 MB
Formato
Archivio WinRAR ZIP
|
5.32 MB | Archivio WinRAR ZIP | Visualizza/Apri |
EF h 19 1127_Presentazione 17-10-2019 all'impresa.pptx
non accessibile
Descrizione: Allegato - Presentazione avanzamento lavori
Dimensione
517.71 kB
Formato
Microsoft Powerpoint XML
|
517.71 kB | Microsoft Powerpoint XML | Visualizza/Apri |
EF i 19 1127_Computo della sicurezza.dsf2
non accessibile
Descrizione: Allegato - Computo della sicurezza
Dimensione
834.27 kB
Formato
CerTus
|
834.27 kB | CerTus | Visualizza/Apri |
EF l 19 1127_Bibliografia.rdf
non accessibile
Descrizione: Allegato - Bibliografia
Dimensione
100.56 kB
Formato
Resource Description Framework Document
|
100.56 kB | Resource Description Framework Document | Visualizza/Apri |
EF 19 1127_Celeste Messina.docx
Open Access dal 27/11/2020
Descrizione: Relazione della tesi
Dimensione
14.15 MB
Formato
Microsoft Word XML
|
14.15 MB | Microsoft Word XML | Visualizza/Apri |
EF 19 1127_Celeste Messina.pdf
Open Access dal 27/11/2020
Descrizione: Relazione della tesi
Dimensione
9.3 MB
Formato
Adobe PDF
|
9.3 MB | Adobe PDF | Visualizza/Apri |
I documenti in POLITesi sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.
https://hdl.handle.net/10589/150783