In Europe, the argument over the relevance of global building sustainability (covering energy, environmental, social, economic, and political issues) is becoming increasingly relevant. In this context, the restoration of existing buildings, particularly those with large volumes and low energy performance, receives considerable attention, however the age of building is another involved factor that must be considered. On the other hand, over the previous few decades, the term of "Building Information Modeling," or BIM, has evolved from a term with a few early adopters to the heart of AEC technology, which encompasses all aspects of building design, construction, and operation. Almost every major design, engineering, and construction firm in the world has switched to BIM from their prior, drawing-based CAD technology. In a more precise sense, BIM in the construction management industry gives not just clients but also project managers the ability to model and estimate crucial project characteristics such as time and cost before they are realized. The major purpose of this project is to represent a decision-making route based on two most important parameter in project management which are cost and time, for reconstructing or renovating an existing building using BIM software in order to achieve a satisfactory energy grade in the building. The cost and time parameters will be used to evaluate this project, which are also influenced by Take Off Quantity and Work Breakdown Structure (WBS). This project makes use of a variety of BIM applications including, 3d modeling for modeling, Quantity take off software, Excel and management platform for cost and time estimation and Energy simulation software .

In Europa, la discussione sulla rilevanza della sostenibilità globale degli edifici (che copre le questioni energetiche, ambientali, sociali, economiche e politiche) sta diventando sempre più rilevante. In questo contesto, il restauro degli edifici esistenti, in particolare quelli di grande volumetria e basse prestazioni energetiche, riceve una notevole attenzione, tuttavia l'età dell'edificio è un altro fattore coinvolto che deve essere considerato. D'altra parte, nei decenni precedenti, il termine di "Building Information Modeling", o BIM, si è evoluto da un termine con alcuni primi utilizzatori al cuore della tecnologia AEC, che comprende tutti gli aspetti della progettazione, costruzione, e funzionamento. Quasi tutte le principali aziende di progettazione, ingegneria e costruzioni nel mondo sono passate al BIM dalla loro precedente tecnologia CAD basata su disegni. In un senso più preciso, il BIM nel settore della gestione delle costruzioni offre non solo ai clienti, ma anche ai project manager la capacità di modellare e stimare le caratteristiche cruciali del progetto come tempi e costi prima che vengano realizzati. Lo scopo principale di questo progetto è rappresentare un percorso decisionale basato su due parametri più importanti nella gestione del progetto che sono il costo e il tempo, per ricostruire o ristrutturare un edificio esistente utilizzando il software BIM al fine di ottenere un grado energetico soddisfacente nell'edificio . I parametri di costo e tempo verranno utilizzati per valutare questo progetto, che sono anche influenzati da Take Off Quantity e Work Breakdown Structure (WBS). Questo progetto fa uso di una varietà di applicazioni BIM tra cui modellazione 3d per la modellazione, software per il calcolo della quantità, Excel e piattaforma di gestione per la stima di costi e tempi e software di simulazione energetica.

Assessment of BIM in construction management : the impact of the WBS, QTO, cost estimation and time analysis on decision making policy for optimization of energy efficency

ASSAREHPOUR, ROKHSAREH
2020/2021

Abstract

In Europe, the argument over the relevance of global building sustainability (covering energy, environmental, social, economic, and political issues) is becoming increasingly relevant. In this context, the restoration of existing buildings, particularly those with large volumes and low energy performance, receives considerable attention, however the age of building is another involved factor that must be considered. On the other hand, over the previous few decades, the term of "Building Information Modeling," or BIM, has evolved from a term with a few early adopters to the heart of AEC technology, which encompasses all aspects of building design, construction, and operation. Almost every major design, engineering, and construction firm in the world has switched to BIM from their prior, drawing-based CAD technology. In a more precise sense, BIM in the construction management industry gives not just clients but also project managers the ability to model and estimate crucial project characteristics such as time and cost before they are realized. The major purpose of this project is to represent a decision-making route based on two most important parameter in project management which are cost and time, for reconstructing or renovating an existing building using BIM software in order to achieve a satisfactory energy grade in the building. The cost and time parameters will be used to evaluate this project, which are also influenced by Take Off Quantity and Work Breakdown Structure (WBS). This project makes use of a variety of BIM applications including, 3d modeling for modeling, Quantity take off software, Excel and management platform for cost and time estimation and Energy simulation software .
Sattanino, Elisa
ARC I - Scuola di Architettura Urbanistica Ingegneria delle Costruzioni
28-apr-2022
2020/2021
In Europa, la discussione sulla rilevanza della sostenibilità globale degli edifici (che copre le questioni energetiche, ambientali, sociali, economiche e politiche) sta diventando sempre più rilevante. In questo contesto, il restauro degli edifici esistenti, in particolare quelli di grande volumetria e basse prestazioni energetiche, riceve una notevole attenzione, tuttavia l'età dell'edificio è un altro fattore coinvolto che deve essere considerato. D'altra parte, nei decenni precedenti, il termine di "Building Information Modeling", o BIM, si è evoluto da un termine con alcuni primi utilizzatori al cuore della tecnologia AEC, che comprende tutti gli aspetti della progettazione, costruzione, e funzionamento. Quasi tutte le principali aziende di progettazione, ingegneria e costruzioni nel mondo sono passate al BIM dalla loro precedente tecnologia CAD basata su disegni. In un senso più preciso, il BIM nel settore della gestione delle costruzioni offre non solo ai clienti, ma anche ai project manager la capacità di modellare e stimare le caratteristiche cruciali del progetto come tempi e costi prima che vengano realizzati. Lo scopo principale di questo progetto è rappresentare un percorso decisionale basato su due parametri più importanti nella gestione del progetto che sono il costo e il tempo, per ricostruire o ristrutturare un edificio esistente utilizzando il software BIM al fine di ottenere un grado energetico soddisfacente nell'edificio . I parametri di costo e tempo verranno utilizzati per valutare questo progetto, che sono anche influenzati da Take Off Quantity e Work Breakdown Structure (WBS). Questo progetto fa uso di una varietà di applicazioni BIM tra cui modellazione 3d per la modellazione, software per il calcolo della quantità, Excel e piattaforma di gestione per la stima di costi e tempi e software di simulazione energetica.
File allegati
File Dimensione Formato  
Thesis - Rokhsareh Assarehpour -Final.pdf

accessibile in internet per tutti

Dimensione 5.6 MB
Formato Adobe PDF
5.6 MB Adobe PDF Visualizza/Apri

I documenti in POLITesi sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/10589/186120