This thesis proposes as its objective the study of various optimization strategies in the implementation of reinforced concrete arch bridges. During the installation of the segments of the rib placing the tiebacks at appropriate points and tensioning the pre-tensions to tie to the same smart values it is possible to generate a advantageous closed configuration in midspan. The substantial advantage is not having to change during the entire implementation of the sections of the bridge the pre-tension of the stays, this improvement involves consequent benefits, both practical and economic. It is therefore important, not only to ensure that each stage of processing the arch is stable, but also that the efforts during the entire process are within a range of values​​, in particular the bending moment acting along the entire process must be less than the allowable moment. Evaluating the process of "back-destruction" could be deduced maximum positive and negative moments at which the emiarch is submitted through the entire installation. The goal of this paper is to propose a set of general strategies that allow to minimize the use of materials, and so costs.

Questa tesi si propone come obiettivo lo studio di varie strategie di ottimizzazione nella messa in opera di ponti arco in calcestruzzo armato. Durante la posa in opera dei segmenti dell'emiarco collocando gli stralli in opportuni punti e tensionando le pre-tensioni da affibbiare agli stessi con valori "smart" è possibile generare una configurazione di chiusura in chiave d'arco vantaggiosa. Il sostanziale vantaggio sta nel non dover modificare durante l'intera messa in opera delle sezioni del ponte le pre-tensioni degli stralli, tale miglioramento comporta conseguenti benefici sia pratici che economici. E' dunque importante, non solo assicurare che per ogni stage di lavorazione l'arco sia stabile, ma anche che gli sforzi durante l'intero processo siano all'interno di un range di valori, in particolare il Momento Flettente agente lungo l'intero processo dovrà essere inferiore al Momento Resistente ammissibile. Valutando il processo di "back destruction" è stato possibile ricavare quelli che sono i momenti massimi negativi e positivi ai quali l'emiarco è sottoposto lungo l'intera messa in opera. L'obbiettivo di questo elaborato è di proporre una serie di strategie generali che permetta di minimizzare l'utilizzo di materiali, quindi costi.

Practical optimization strategies In cantilever launching method of arch bridges

IEVA, CLAUDIO
2013/2014

Abstract

This thesis proposes as its objective the study of various optimization strategies in the implementation of reinforced concrete arch bridges. During the installation of the segments of the rib placing the tiebacks at appropriate points and tensioning the pre-tensions to tie to the same smart values it is possible to generate a advantageous closed configuration in midspan. The substantial advantage is not having to change during the entire implementation of the sections of the bridge the pre-tension of the stays, this improvement involves consequent benefits, both practical and economic. It is therefore important, not only to ensure that each stage of processing the arch is stable, but also that the efforts during the entire process are within a range of values​​, in particular the bending moment acting along the entire process must be less than the allowable moment. Evaluating the process of "back-destruction" could be deduced maximum positive and negative moments at which the emiarch is submitted through the entire installation. The goal of this paper is to propose a set of general strategies that allow to minimize the use of materials, and so costs.
ING I - Scuola di Ingegneria Civile, Ambientale e Territoriale
25-lug-2014
2013/2014
Questa tesi si propone come obiettivo lo studio di varie strategie di ottimizzazione nella messa in opera di ponti arco in calcestruzzo armato. Durante la posa in opera dei segmenti dell'emiarco collocando gli stralli in opportuni punti e tensionando le pre-tensioni da affibbiare agli stessi con valori "smart" è possibile generare una configurazione di chiusura in chiave d'arco vantaggiosa. Il sostanziale vantaggio sta nel non dover modificare durante l'intera messa in opera delle sezioni del ponte le pre-tensioni degli stralli, tale miglioramento comporta conseguenti benefici sia pratici che economici. E' dunque importante, non solo assicurare che per ogni stage di lavorazione l'arco sia stabile, ma anche che gli sforzi durante l'intero processo siano all'interno di un range di valori, in particolare il Momento Flettente agente lungo l'intero processo dovrà essere inferiore al Momento Resistente ammissibile. Valutando il processo di "back destruction" è stato possibile ricavare quelli che sono i momenti massimi negativi e positivi ai quali l'emiarco è sottoposto lungo l'intera messa in opera. L'obbiettivo di questo elaborato è di proporre una serie di strategie generali che permetta di minimizzare l'utilizzo di materiali, quindi costi.
Tesi di laurea Magistrale
File allegati
File Dimensione Formato  
IevaClaudioThesis.pdf

accessibile in internet per tutti

Descrizione: Practical Optimization Strategies In Cantilever Launching Method Of Arch Bridges
Dimensione 14.71 MB
Formato Adobe PDF
14.71 MB Adobe PDF Visualizza/Apri

I documenti in POLITesi sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/10589/94258